Johor data centres hit ‘time to power’ bottleneck
Approvals and grid delivery delays – not generation capacity – are determining which data centre projects move ahead on schedule
[KUALA LUMPUR] Johor’s bottleneck is no longer power generation but grid delivery, with connection timelines now determining which data centre projects move on and which fall behind, said industry watchers.
The consequences of that shift are already visible. Johor rejected up to 30 per cent of new data-centre applications in 2024, based on industry guidance published this month.
The report by Area Market Intelligence cited misaligned utility timelines, lack of clarity on the responsibility for substation infrastructure, and planning issues that were identified late in the day for the delays and rejections.
TRENDING NOW
Singapore households’ net wealth up, but also taking on more debt such as home loans
With new S$10 million HQ, Jumbo Group looks to Shanghai-focused China strategy, premium dining for growth
Up to 11 new condo projects with 3,550 units lined up for H2 launch as price ceilings emerge
Yeo’s, Tiger Beer and now Gardenia – flight of food manufacturing from Singapore might be just as planned