BASF starts layoff process at Finland site after permit problems

Published Thu, Apr 11, 2024 · 06:13 PM

GERMANY’S BASF said on Thursday (Apr 11) that it has begun the layoff process at its Harjavalta site in Finland after facing permitting issues from the relevant authorities.

The so-called change negotiations, a required process in Finland if an employer is considering layoffs, will begin on Monday and last for six weeks, according to BASF.

The company employs a double-digit number of people in Harjavalta, all of whom are potentially affected by the move.

The decision comes after an administrative court cancelled a temporary permit for the new plant for precursors for cathode materials in February.

The company had received initial approval from the relevant authorities in 2020, but this was withdrawn following objections from NGOs due to environmental concerns. The plant was originally scheduled to go into operation in 2022.

The further postponement and uncertainty regarding a formal start have long-term financial implications, said BASF, which has invested a three-digit million-euro sum in the project.

GET BT IN YOUR INBOX DAILY

Start and end each day with the latest news stories and analyses delivered straight to your inbox.

VIEW ALL

“The decision to initiate these negotiations was made because of the lengthy permitting process with unclear outcomes, leading to an unpredictable timeframe for receiving a final, unappealable permit,” said BASF in a statement.

However, a decision by the responsible authorities could still be made this year, said a company spokesperson. REUTERS

KEYWORDS IN THIS ARTICLE

READ MORE

BT is now on Telegram!

For daily updates on weekdays and specially selected content for the weekend. Subscribe to  t.me/BizTimes

Energy & Commodities

SUPPORT SOUTH-EAST ASIA'S LEADING FINANCIAL DAILY

Get the latest coverage and full access to all BT premium content.

SUBSCRIBE NOW

Browse corporate subscription here