Oxley unit, former contractor in dispute over The Peak project
Oxley Gem (Cambodia) is seeking compensation for alleged breaches of obligations; SGW is counter-suing
Nisha Ramchandani
Singapore
A UNIT of Oxley Holdings has started legal proceedings against its former contractor, Sino Great Wall Engineering Co (SGW), in a dispute over its project The Peak in Cambodia.
On April 1, Oxley Gem (Cambodia) commenced formal legal proceedings in Singapore against SGW to seek compensation for alleged damages suffered due to SGW's repeated breaches of its obligations, Oxley said in a filing to the Singapore Exchange late Thursday night.
Oxley Gem had called on the two performance bonds provided by SGW for the project and terminated the contract in October last year after significant delays to the project, it had said previously.
At the time of termination, Oxley alleged SGW had only completed 53 per cent of the work under contract, while the end of the contract term was January 2020.
"Under the contract, Oxley Gem is entitled to withhold further payments to SGW until the damages due to Oxley Gem from SGW's breaches have been established," said a spokesperson for Oxley, adding that the amount of damages that Oxley Gem is claiming far exceeds the amount that has been withheld.
For its part, SGW is seeking "outstanding payment" from Oxley Gem, in addition to "compensation of the loss caused by them", said a spokesman for SGW, who alleges that it had completed about 70 per cent of the project.
"SGW had separately filed a Motion of Objection to Ruling of Provisional Disposition (and an) Injunction against Oxley Gem in March 2020," said the spokesman. These are understood to be filed in Cambodia.
The SGW spokesman added: "Oxley Gem had terminated the contract three months prior to the contractual completion date and did not settle the outstanding payment due to SGW, including the claimed guarantee bonds, (which is) 10 per cent of the contract amount. (Oxley Gem) withheld SGW's property on site unlawfully and evicted SGW's workers, who were dismantling temporary materials, from the site forcefully."
The property in question is understood to include equipment and tools.
According to Oxley, SGW's property was rounded up at the instructions of the Cambodian court bailiff and placed at a site as at April 17 and is expected to be returned to SGW in line with formal court processes.
Oxley Gem had on Feb 14 obtained an injunction order from the Cambodian courts as it said SGW refused to vacate the site and was wrongfully occupying it, causing further delays as a newly appointed main contractor could not start work.
From Feb 25, SGW was then evicted from the project site by the court bailiff, who was understood to be handling the eviction process.
While SGW later objected to the eviction order, the Cambodian courts rejected the objection, Oxley said.
SGW is a unit of debt-ridden Sino Great Wall, which was delisted from the Shenzhen Stock Exchange in January this year pursuant to listing rules after its shares closed below one yuan on consecutive trading days spanning Sept 26-Oct 30 last year.
For 1H19, Sino Great Wall posted a net loss of about RMB1.4 billion (S$282 million), versus a net profit of RMB144 million a year ago.
In this week's filing to SGX, Oxley confirmed that SGW had in mid-March this year applied to the Cambodian courts to get Oxley Gem to suspend work on the Peak.
That hearing has been rescheduled to a future date to be determined after SGW failed to attend the hearing for its own application, said Oxley.
"Oxley Gem has been advised by its lawyers that SGW has no basis for its application and is seeking to dismiss SGW's application," it added.
Meanwhile, the new main contractor, China Railway Urban Construction Group, has commenced work on The Peak.
Completion of the project - a 55-storey mixed development with a hotel, offices, residential units and a retail mall - is now slated to take place progressively from mid 2020 to 2021.
Shares in Oxley closed at 22 Singapore cents on Friday, up half a cent.