San Teh's subsidiary ordered by Yunnan court to pay 11.3m yuan to contractor
SAN Teh announced on Wednesday that its subsidiary Dali San Teh Xing Real Estate has been ordered by the Yunnan court to pay approximately 11.3 million yuan (S$2.3 million) to its main contractor for the return of security deposit of eight million yuan and compensation for work stoppage damages of approximately 4.4 million yuan.
The above sum was offset by progress payment overbilled by the contractor of approximately 1.1 million yuan.
The subsidiary was also ordered to pay interest on the security deposit of eight million yuan calculated based on the People's Bank of China borrowing rate for the period from Sep 11, 2014 up to the payment date, and for the contractor to return the construction site.
The above judgement is expected to have a negative impact of approximately 4.7 million yuan on the group's income statement for the second quarter of the financial year ended Dec 31, 2018 arising from the provision for litigation.
The subsidiary is planning to appeal the ruling.
Share with us your feedback on BT's products and services
TRENDING NOW
Extra S$300 in CDC Vouchers, U-Save rebates for households as part of S$900 million support package
Singtel explores Nasdaq-SGX dual listing for data centre arm Nxera, local data centre Reit
Singapore banks’ battle for wealth talent goes beyond private bankers
Singapore rolls out S$900 million support package for businesses, households in light of Iran war