AGO report: National Arts Council paid consultants S$0.41m to build S$0.47m bin centre
DeeperDive is a beta AI feature. Refer to full articles for the facts.
THE National Arts Council paid a S$0.41 million consultancy fee for the construction of a bin centre costing S$0.47 million, the Auditor-General's Office (AGO) report on accounts of government entities and statutory bodies for the financial year 2015/16 on Tuesday showed.
"There was inadequate assessment on the reasonableness of the exceptionally high consultancy fee, at 87.2 per cent of the cost of construction," said the report.
AGO's test checks of contracts for the Victoria Theatre and Victoria Concert Hall Redevelopment project also showed 47 out of 164 variation works were carried out before approvals were given. The delays in obtaining approval were up to 3.5 years.
"The large number of instances indicated a breakdown in the controls put in place to ensure that variations were properly justified and approved before works commenced," AGO said.
Copyright SPH Media. All rights reserved.
TRENDING NOW
Singaporeans can now buy record amount of yen per Singdollar
Beijing’s calculated silence on the Iran war
China pips the US if Asean is forced to choose, but analysts warn against reading it like a sports result
StarHub hands Ensign InfoSecurity control back to Temasek in S$115 million deal, books S$200 million gain