柔佛州数据中心遭遇“供电时间”瓶颈
决定数据中心项目能否按期推进的关键,在于审批和电网交付的延迟,而非发电容量。
DeeperDive is a beta AI feature. Refer to full articles for the facts.
本文由AI辅助翻译
【吉隆坡】业内观察人士表示,柔佛州面临的瓶颈已不再是发电量,而是电网交付。目前,电网接入的时间表正决定着哪些数据中心项目能够继续推进,哪些则会落后。
这一转变带来的影响已然显现。根据本月发布的行业指南,柔佛州在2024年拒绝了高达30%的新数据中心申请。
Area Market Intelligence 发布的报告指出,公用事业时间表不匹配、变电站基础设施的责任归属不明确,以及在项目后期才发现的规划问题,是导致项目延迟和被拒的主要原因。